Bridge protection on the Neuenkamp Rhine Bridge (A40)

At the Rheinbrücke Neuenkamp on the A40 in Duisburg, traffic lanes protected both directions: from 2018 to 2023 in the direction of Essen and from 2019 to 2024 in the direction of Venlo. Here, almost all modules of the system were used together.

The task

There are restrictions for heavy traffic on the Rheinbrücke Neuenkamp. To ensure compliance with these restrictions, a control system is needed that operates around the clock – without personnel on site and without stopping the rest of traffic.

The solution of traffic-lines

Installed: 5 lanes of Weigh in Motion, barrier system, weighing area with BAG interface, foundationless traffic sign bridge.

  • Weigh in Motion weighs each vehicle at full speed and determines the axle loads.
  • An automated barrier system directs vehicles over the limit value before the structure is built.
  • A staging area with an interface to the Federal Office for Logistics and Mobility (BALM, formerly BAG) enables the monitoring of exiting vehicles.
  • Unfounded traffic sign bridges carry signage and signals above the roadway.

More about the system: Bridge protection and Vehicle differentiation (FDS).

The project in the video

Photos of the project

Project data at a glance

  • Building: Neuenkamp Rhine Bridge
  • Street: A40
  • Location: Duisburg
  • Period: 2018–2024
  • Performance: Bridge protection
  • Systems: 5 lanes with Weigh in Motion, barrier system, weighing area with BAG interface, foundation-free sign gantry

You can find an overview of all projects in our References.

Are you planning a bridge protection or axle load measurement?

We advise you from the feasibility study to planning and commissioning. Whether buying or renting – contact us.